DESIGN OF A PLANT TO PRODUCE 60,000 TONNES OF 2-ETHYL HEXANOL FROM PROPELENE AND SYNTHESIS GAS

Code: 8CC7E4AABB0421  Price: 4,000   61 Pages     Chapter 1-5    6344 Views

DESIGN OF A PLANT TO PRODUCE 60,000 TONNES OF 2-ETHYL HEXANOL FROM PROPELENE AND SYNTHESIS GAS

ABSTRACT

Plant design which is an iterative procedure with a route of procession from the input or feed to the stated objectives, amidst intervening constraints, requires a careful, well- thought- out, comprehensive specifications of the defined or desired requirements.

The stated objective in this case is the design of a 60,000 tons/year capacity of a 2- Ethyl Hexanol (C8H18O) Plant. While many processes exist at producing 2-Ethyl Hexanol (2- EH), such as the Acetaldehyde Route and others developed by Shell Corporation etc., the Oxo Process route utilizing propylene and synthesis gas as feed components was the selected route for this design work. However, important modifications were implemented to the process description for effective process optimization, such as to improve the conversion of efficiencies of process equipment by aid of recycle processes.

The oxo synthesis began by reacting propylene feed and synthesis gas (CO + H2) in a Rhodium triphenylphosphine catalyzed hydroformylation reaction.

An acceptable design must present a process that is capable of operating under conditions which will yield a profit. A simple costing procedure was carried out for the 2- EH Plant to determine if the design is feasible economically or not based on certain estimates.

Estimates were prepared using data and Chemical Engineering plant cost index method in Literature, considering Port Harcourt, Rivers State, Nigeria as the location of the plant. Old cost information was obtained and extrapolated using the Index Method to the present 2016 costs. These costs were evaluated in U. S dollars. The Purchased Cost of Equipment (PCE) was valued at $3,150,153.93, while the Physical

Plant Costs (PPC) or direct costs was obtained by the factorial costing method at 3.4 times PCE, and valued at $10,62,544.69. Indirect costs were the expenses which are not directly involved with material and labor which included design and engineering, contractor’s fee etc, and were valued at $5,040,246.29. The Fixed Capital Investment (FCI) was obtained by summing up the direct and indirect costs, and valued at $16,002,790.98. The Working Capital was 12% of the FCI and both gave the Total Capital Investment of $17,923,125.90. The start- up cost of plant for production was evaluated at 10% of TCI.

With a selling price at $1.74/kg, the 60,000 tons/year of 2- Ethyl hexanol plant is expected to have a net profit of $22,125,469.76 and a payback period of 2.8 years. However, procedures for safe operation and start- up of the 60,000 tons/year 2-Ethylhexanol Plant was documented.

DESIGN OF A PLANT TO PRODUCE 60,000 TONNES OF 2-ETHYL HEXANOL FROM PROPELENE AND SYNTHESIS GAS


Terms of Use: This is an academic paper. Students should NOT copy our materials word to word, as we DO NOT encourage Plagiarism. Only use as a guide in developing your original research work. Thanks.

Disclaimer: All undertaking works, records, and reports posted on this website, eprojectguide.com are the property/copyright of their individual proprietors. They are for research reference/direction purposes and the works are publicly supported. Do not present another person’s work as your own to maintain a strategic distance from counterfeiting its results. Use it as a guide and not duplicate the work in exactly the same words (verbatim). eprojectguide.com is a vault of exploration works simply like academia.edu, researchgate.net, scribd.com, docsity.com, course hero, and numerous different stages where clients transfer works. The paid membership on eprojectguide.com is a method by which the site is kept up to help Open Education. In the event that you see your work posted here, and you need it to be eliminated/credited, it would be ideal if you call us on +2348064699975 or send us a mail along with the web address linked to the work, to eprojectguide@gmail.com. We will answer to and honor each solicitation. Kindly note notification it might take up to 24 – 48 hours to handle your solicitation.

Material Information
  • ₦4,000.00 1 Price:
  • 61 2 No. of Pages:
  • 5 3 No. of Chapters:
  • No 4 Has Implementation:
FOR ENQUIRIES WE ARE AVAILABLE 24/7

Contact us on

DEPARTMENT
LAW